Mosman Council Spit East Upgrade Shifts To Stage 2A

The Spit East Road upgrade in Mosman, which commenced in October 2018, has entered stage 2A of its work plan in March 2019. As a result, access to this area will be limited until the project’s completion in June.

The upgrade’s progress, however, has been on schedule and locals will soon be able to benefit from the following facilities:


Stage 1A
new bus bay, bus shelter
new laneway by the foreshore
completed

Stage 1B
new bike hoops, waiting area seats
new landscaping, trees & garden beds
completed

Stage 2A
new parking area, signages
new footpaths to the commercial area
March to April 2019

Stage 2B
new paving, additional landscapingMay to June 2019



“The objectives of the Spit Road streetscape upgrade are to enhance pedestrian safety and accessibility, mitigate flooding, enhance the landscaping and amenity of the area, and improve access to public transport,” as cited in the upgrade’s report.

Photo Credit: Mosman Council

Funding for the Spit East upgrade comes from the B-Line project sponsored by the State Government. The Council had a series of consultations with the public since 2016 to determine what should be prioritised in the upgrade.